RECONSTRUCTION OF OREROKPE-EKU ROAD (SECTION II) FROM 13 + 000 TO EKU AT CH 25 + 530, OKPE AND ETHIOPE EAST LOCAL GOVERNMENT AREA
Project Description
The scope of the work for the 12.530km length of road includes removal of unsuitable materials, scarification of failed existing bituminous surfacing, scarification and pulverization of existing bituminous surfacing on the stable sections as fillings, sharp sand filling, soil stabilization, concrete works comprising of crushed stone base and asphaltic binder on 13.5m carriageway width inclusive of the shoulders and asphaltic wearing course on the 8m carriagewat width.
The project will reduce travel time and transportation costs, enhance access to markets, educational and healthcare facilities, stimulate trade and investment, strengthen socio-economic integration between communities, and contribute to sustainable infrastructure development and economic growth across Okpe and Ethiope East Local Government Areas.
Sustainable Development Goals (SDGs) Impacts
Decent Work and Economic Growth
Industry, Innovation and Infrastructure
Sustainable Cities and Communities
Project Information
Contract Period
14 MONTHS
Progress
Ministry/MDA
STATE TENDERS BOARD
CNO Reference
DSPPC/CNO/2138
Year
2026
Date Awarded
02/06/2026
Expected Completion
30/07/2027
Location (LGA)
Okpe, Ethiope East
Address
Orerokpe-Eku Road, Abraka
Contractor
LEBTECH CONSTRUCTION LIMITED
Category
Works
Coordinates
Lat: 5.63971550,
Long:
5.89079400,
Lat: 5.78943210,
Long:
6.10234680,